Materials used in the construction of API 650 SUG II tanks

The API 650 SUG II tanks stiffener ring and backing strip (if used) are primary components, and they shall comply with the requirements of API 620 storage steel tank Q.2.1. The stiffener rings may be fabricated from plate using an intermittent weld on alternating sides between the web and the flange.
Except for aluminum or stainless steel tanks, all fillet welds shall consist of a minimum of two passes. The ends of the fillet welds shall be 2 in. from the rat hole (see Figure Q-1), and these welds shall be deposited by starting 2 in. from the rat hole and welding away from the rat hole. An acceptable alternative to the detail that includes stopping fillet welds 2 in. short of the rat hole would be to weld continuously through the rat hole from one side of the stiffener to the opposite side. All craters in fillet welds shall be repaired by back welding.API 650 petroleum storage tank has the advantage of long economic life: because there is no gas space on the liquid surface in the internal floating roof API 650 SUG II tanks storage tank, the vibration generated during the transportation of liquid inside and outside the tank is reduced.This customer is a leading Engineering, Procurement and Construction company serving the Hydrocarbon and Chemical industries spanning Oil & Gas, Petrochemical, Refining, Fertilizer and related sectors in India. The A335 Grade P5 Steel Pipe and P9 API 650 SUG II tanks Seamless Steel Pipe we supplied is for EIL refineries project.Prefabrication requirements of API 650 SUG II tanks, large vertical storage tank wall panels:
1. The prefabrication of wall panel shall be processed in strict accordance with the requirements of the drawings, and inspection records shall be made.
2. After the wall panel is rolled, it should be placed on the platform for inspection with a template. In the vertical direction, use a straight-line template to check, the gap should not be greater than 2 mm, and in the horizontal direction, use an arc-shaped template to check, and the interval should not be greater than 4 mm.
3. When wall panels are rounded, attention should be paid to prevent irreversible plastic deformation caused by external forces. After rolling, it should be placed on the platform for inspection, and then placed on the prepared mold.After-sales service is an important part of measuring a product good or not. After sales service can't be ignored. Good service can really make consumers feel relieved. We have always done a good job in after-sales service, so as to bring consumers a better reference when purchasing and a better experience during use of our steel materials. We will call back and follow up the performance of our steel products regularly.

Have a question? Get a Free Consultation

If you are interested in our storage tanks, you can get contact with us through online consulting, demand table submission, e-mails and telephones.

Corporate Office

High-Tech Development Zone, Zhengzhou, China

Contact us

+86-371-86151527
[email protected]

Send a Message!